The contract agreement was signed on 6th December 2017 between NEC and Jagdulla Hydropower Company Ltd (JHPCL) to conduct the Feasibility/ Detail Engineering Study of JHEP incorporating the technical, financial, and relevant aspects of the project development based on detailed survey and investigations including preparation of bidding documents of JHEP. The study was completed in July 2021.
Location: Dolpa District, Karnali Province
Type of Project: Peaking Run of River Type
Design Discharge: 16.2 m3/s
Gross Head: 786.6 m
Installed Capacity: 106 MW
Annual Energy Generation: 623 GWh
Evacuation Substation: NEA Bafikot Substation, Rukum District